Volume 18, Issue 91  |  November 13, 2026

Slide

City reviews progress on $69 million in infrastructure projects, focuses on realistic timelines

By SARA HALL

Public works staff updated City Council on October 22 on the status and progress of ongoing capital projects, highlighting approximately $69 million in public infrastructure investments.

Councilmembers adopted the fiscal year 2026-27 budget on June 23, which included 10 new Capital Improvement Program (CIP) projects. There are also 39 ongoing projects currently in design or under construction.

“This is good, I’m glad you gave us this update,” said Councilmember Sue Kempf.

She also asked if staff had changed the pacing of projects after they “scrubbed” the CIP list.

“It looks like it’s a little bit more realistic in terms of what we’ll be doing in the future,” Kempf said.

Public Works Acting Director Tom Perez confirmed the department has made adjustments over the past few years.

“We really want to start programming to really set an expectation of projects that we feel will get done the years that they’re programmed,” he said.

There are exceptions, he added. The focus is on realistic timelines and acknowledging that some projects may seem simple on the surface, but take time to move through the process, including conducting public outreach or navigating delays involving other agencies.

“It’d be nice to think we could expedite and push everything as fast as we can, but sometimes there’s just things that are beyond our control,” Perez said. “We really want to start acknowledging that and, at a bare minimum, we may not like the timeline, but if we understand that it is true and realistic that’s what we really want to aim for.”

Capital Program Manager Pierre Sawaya highlighted several recently completed projects, including the Emergency Operations Center and sidewalk repairs in North Laguna.

Click on photo for a larger image

Photo by Mary Hurlbut

The interior of the city’s new Emergency Operations Center

Other projects just kicking off or currently underway include the Anita lift station and beach access reconstruction, Downtown street resurfacing and Agate Street storm drain improvements. Projects in the bidding and award phase include Jahraus Park renovation, Coast Highway median landscaping and the South Laguna fire station.

Councilmember Bob Whalen expressed frustration with the delay between council approval of the fire station and when the project actually goes out to bid.

“How do we tighten that up?” Whalen asked.

Perez noted that Planning Commission review could prompt significant changes. Some projects may be ready to proceed at that point, he added, but typically there is still substantial work to be done, including building plan checks and final design permits.

“That’s maybe something we can work on clarifying what all happens at these different phases of work,” Perez commented.

A number of projects are also currently in design, including the Main Beach boardwalk rehabilitation, enclosed lifeguard towers, beach access and street improvements and library interior renovation.

The library project consists primarily of new carpeting and painting, Sawaya said.

“We’ve sort of reimagined the space inside the library,” he commented.

Some spaces have been rearranged to make the library more inclusive for the public, Sawaya explained. The project also includes earthquake-compliant shelving and heating, ventilation and air conditioning improvements.

Some funding had already been programmed, and the county committed to providing additional money for the improvements, Sawaya noted.

Click open story button to continue reading…

There was also discussion about the beach access projects. Assistant City Manager Jeremy Frimond noted that a sand study planned for early 2027 will analyze how much sand has been retained or returned to shore. Regarding other data that could help the city plan for coastal resiliency, he confirmed opportunities to work with partner organizations to discuss coastal hardening and best practices.

Mayor Mark Orgill suggested creating a dedicated city webpage to keep residents informed about the situation.

Whalen recommended city committees review the recent state climate assessment report to determine whether there are any local implications or steps the city should be taking.

The California Coastal Commission is committed to being responsive to changing conditions and is under considerable pressure from the governor’s office to streamline the permitting process, added Mayor Pro Tem Hallie Jones.

“Sand replenishment itself is obviously a little bit of a problematic scenario from an environmental perspective but … everybody is rowing in the same direction on this right now,” Jones commented. “I think we’re in good shape.”

~~~~~~~~

Sara Hall covers City Hall and is a regular contributor to Stu News Laguna.